NH Construction Law
  • Home
  • Blog
  • Links

#136:  Fixed Price vs. “Cost Plus” Contracts: Some Considerations

6/23/2024

0 Comments

 
When contracting parties agree to a fixed price or lump sum amount for a defined scope of work, the contractor is generally obligated to build that scope of work for that price regardless of what it costs him to do so or what unmentioned obstacles he may face.  His price will typically be set to cover overhead costs and a reasonable profit.  And time is money; all other things being equal, the sooner the contractor completes the work, the more profit he will make.  Framing a building in a week rather than two, or drywalling a room in a day rather than two, saves money and acts as an incentive to move fast.
 
Some think that this incentive spawns corner-cutting and less attention to detail, particularly when an owner lacks the resources or (as in most residential construction) the expertise to catch poor workmanship, which is often covered up before any opportunity for observation.  A measure of trust is accordingly essential in fixed price contracts.
 
If quality is an owner’s priority, some think that “cost-plus-a-fee” contracts – reimbursement for labor and materials expenses, plus either a percentage or a fixed amount for overhead and profit – are the way to go.  This eliminates incentives to cut corners or rush a project through, as the time spent on “getting it right” will be compensated.  But that time may include many man-hours spent reworking areas of the construction that, if the worker were more skilled, should have been built properly the first time.  The productivity of the contractor’s workforce is not easy for the inexperienced owner to gauge.  A measure of trust is accordingly essential in cost plus contracts.
 
In the commercial setting, various form contracts are designed to lessen the risks for both fixed price and cost plus contracts by changing “trust” to “trust but verify.”  Plans and specifications are more detailed; architects or owner reps observe the work and approve payment; differing site conditions clauses are included; scheduling is monitored; subcontractors are often approved in advance; and in cost-plus contracts a “not to exceed” or “guaranteed maximum” price is often agreed upon, reimbursables are defined with care, and the back-up for reimbursable expenses is scrutinized.  Residential contracts rarely include such provisions.
 
So which type of contract is better?  There is no one-size-fits-all answer, but here are some considerations:
 
1.  Is the scope of work uncertain, such that many changes are likely to occur during the project?  Cost plus contracts may offer more flexibility and transparency for both parties, and change orders (which is where many fixed price contractors earn their highest return) are less dominant.
 
2.  Are quantities uncertain?  “Unit prices” (fixed amounts per linear or cubic yard of work performed or per ton of materials used) can lessen the impact of quantitative uncertainties, and reduce the risk of fixed price contracts for contractors and thus the cost for owners.
 
3.  Is the completion date of paramount importance?  A cost plus contract is likely to be lower on a busy contractor’s priority list than his fixed price arrangements, and take longer to complete.  And the tracking of expenses by the contractor is project management time devoted to paperwork rather than production.
 
4.  Is saving as much money as possible paramount?  In a tight construction market with limited availability of builders, fixed price contracts tend to be padded to deal with uncertainties, contingencies, mistakes, etc.
 
5.  Is the budget set in stone?  A fixed price contract gives greater certainty.
 
6.  Are “allowance” items a large part of the price?  These make fixed price contracts a hybrid contract, as allowance items are cost-plus elements of an otherwise fixed price arrangement.
 
Clarity on which type of contract is in place is a must.  In the residential setting I occasionally see agreement to what is styled as an “estimate,” followed by disagreement over whether that estimate was really intended as a fixed price when, almost inevitably, the job comes in over budget.   The parties should tighten this up at the beginning, at a minimum by limiting the contractor to staying within some agreed percentage of his estimate.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly