New Hampshire’s mechanic’s lien statute, RSA 447:2, gives a lien to those who “perform labor, provide professional design services, or furnish materials” to improve someone’s real estate.  The lien “provides security against the property owner for the value of the labor or materials rendered.”  Pine Gravel, Inc. v. Cianchette, 128 N.H. 460, 464 (1986).  The statute is silent on how that “value” is measured, but the common practice has been to base the lien amount on the agreed price for the labor and materials provided – which naturally includes a markup for profit and overhead.  This approach is supported by a reference in Anderson v. Shattuck, 76 N.H. 240, 247 (1911), to “the contract price, which is the measure of the protection afforded by the lien.” 
 
Using the agreed contract price as the measure of lien value has some appeal because it indicates the owner’s own view on what the labor and materials are worth.  But that logic fails when the owner and lienor did not contract directly.  Anderson concerned a general contractor’s lien rather than a subcontractor’s lien – a distinction that Maine’s Supreme Court found significant in Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., 151 Me. 145, 148, 116 A.2d 664, 666 (1955):  “When by express contract the parties fix the compensation to be paid for full and complete performance of the contract, they have themselves established the debt to be secured by lien. In a sense they have by binding agreement determined the extent to which the owner’s property will be enhanced by the labor and materials to be incorporated in the realty, and to that extent the contractor is protected by lien. When, as here, the owner is not party to the contract, the determination must be as to what is the fair and reasonable value of the labor and materials in place.” 
 
Calculating the fair and reasonable value of labor and materials is no easy task.  Some states presume that the subcontract price establishes reasonable value for lien purposes, and put the owner to the burden of proving otherwise.  Typical is Diener v. Cubbage, 259 Md. 555, 561, 270 A.2d 471, 474 (1970) (“while the contract is not binding on the owner, the contract price is nonetheless prima facie proof of the reasonable value, and the owner has the burden of introducing evidence to show unreasonableness”).
 
Court decisions under New Hampshire’s public works payment bond statute, RSA 447:16, which likewise provides security for labor and materials without mention of overhead or profit, do not appear to have questioned the propriety of a bond claim based on the subcontract price.  Cases under the federal Miller Act – the analogue to RSA 447:16 for federal projects – expressly support including overhead and profit.  Arthur N. Olive Co. v. U.S. for Use & Benefit of Marino, 297 F.2d 70, 73 (1st Cir.1961) (“Out-of-pocket expense is not the limit of the fair value of labor and materials.”)  This would seem to overturn United States ex rel. Henie v. Great American Indemnity Co., 30 F.Supp. 613 (D.N.H. 1939), which held that a subcontractor could recover under a payment bond only its actual cost of labor and materials, and not any profit thereon.
 
For both general contractors and subcontractors, lost profit on work not performed is never included in the lien, which “increase[es] in amount according to the progress of the work until performance is completed,” Boulia–Gorrell Lumber Co. v. East Coast Realty Co., 84 N.H. 174, 177 (1929).  This makes sense.  When mechanic’s liens transfer value added by improvements from the owner to the unpaid lienor, the owner’s net wealth is unaffected.  Similarly, RSA 447:9 gives mechanic’s liens priority over other pre-existing liens because the increased value floats all boats, leaving them with no less draw under their hulls.  But this rationale applies only when the amount of the lien matches the increase in value.  Unperformed work doesn’t increase value.
 
The same is true of delay damages.  Nevertheless, H.E. Contracting v. Franklin Pierce College, 360 F.Supp.2d 289, 295 (D.N.H. 2005), added delay damages to a general contractor’s lien amount.  I couldn’t tell you why!

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly