NH Construction Law
  • Home
  • Blog
  • Links

#146:  Design-Build Contracts and the Spearin Doctrine: an Update

5/24/2025

0 Comments

 
Several years back I blogged (#36) on how design-build contracting – combining design and construction responsibilities in a single phased contract – might impact a contractor’s liability for design defects where there is joint participation by owner and contractor in the design.  I pointed out the approach taken in Coghlin Electrical Contractors, Inc. v. Gilbane Building Co., 472 Mass. 549 (2015), which held that because the owner has the ultimate decision on acceptance or rejection of the design, the design-build contractor is not a “guarantor against all design defects.”

Sometimes a design-build contractor is obliged to use an architect/engineer’s preliminary design as a template. (See Arco Ingenieros, S.A. v. CDM International, Inc., 368 F.Supp.3d 256, 259 (D.Mass. 2019), in which a design-builder was required to “use the preliminary designs to create final designs.”)  In such cases, the Spearin doctrine – the owner’s implied warranty of sufficiency of design specifications (see Blog #24) – may still be in the mix.  As described by AAB Joint Venture v. United States, 75 Fed. Cl. 414, 428-29 (2007), “the implied warranty is that the specifications will result in a satisfactory, acceptable, or adequate result; short of that, the specifications are defective and the contractor is entitled to an equitable adjustment.”

Because Spearin only applies to design specifications, a contractor’s Spearin claim turns on whether the specification in question is a true design spec – one that leaves no discretion to the contractor to deviate from it – or is, rather, a performance spec which leaves it to the contractor to figure out how to achieve a required performance level.

A recent Federal Circuit Court of Appeals decision, Balfour Beatty Construction, LLC v. Administrator of the General Services Administration, 2025 WL 798865 (Fed. Cir. March 13, 2025), sheds some light on the issue.  The project was to construct and expand phase two of the central utilities plant for the Department of Homeland Security headquarters in Washington D.C. The design-build contractor in that case was presented by GSA with preliminary design drawings about 30% complete – so-called “bridging” documents – and was obliged both to validate the design and to complete it.  GSA’s bid solicitation contained this caveat:

“The Bridging Documents are conceptual in nature and are intended to depict the overall intent of the project terms of general design concept, the major architectural elements, and describe the required performance of the other systems. As Bridging Documents they are preliminary in nature, are not fully coordinated and are not intended to indicate or describe the scope of work required for the full performance or completion of the project.”

The design-build contractor found errors in the bridging documents that required significant redesign – specifically, a drawing that directed the contractor to match an existing foundation thickness of 18 inches, belied by calculations from GSA consultants that called for a 24-inch foundation – and even that turned out to be inadequate.  The contractor ultimately installed a 43-inch slab and submitted a claim for increased costs, which the contracting officer rejected.  The Board of Contract Appeals upheld that rejection, concluding that the discrepancy “should have caused Balfour to raise the issue before contract award.”  But the Court of Appeals disagreed.  Finding that “the drawing is sufficiently definite to constitute a design specification,” the Court ruled that “there was an implied warranty with respect to the mat slab thickness.”  Accordingly, the contractor was entitled to extra compensation for putting in a thicker slab.

[The contractor did not fare so well on its second claim, for additional costs related to meeting ventilation requirements when compliant generators were too large to fit in the building space.  The Court upheld the Board’s rejection of this claim, noting that GSA had made clear to bidders that compliance with ventilation requirements must be assumed as the basis for bids.  The Court ruled that “The ventilation requirements were set out as a performance specification, and therefore, no implied warranty attached.”]

Despite the outcome, it would be a mistake to read this case as approving of a bidder’s silence in the face of an obvious discrepancy in the bid documents.  The safer course is to raise the issue with the owner before submitting a bid.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly