NH Construction Law
  • Home
  • Blog
  • Links

#152:  Retainage and Performance Bonds

12/31/2025

0 Comments

 
In commercial and governmental construction contracts, it is common for owners to retain from general contractors, and for general contractors to retain from subcontractors, some percentage of progress payments earned until substantial completion (or, less frequently, final completion) of the contract has been achieved.  Its purpose is to protect the holder from the financial impact of a breach of contract by downstream parties.  Any portion of the retainage not used to correct a breach must be returned.  Parem Contracting Corp. v. Welch Construction Co., Inc., 128 N.H. 254, 257 (1986) (“A party owed a retainage does not forfeit the amount owed if it breaks the contract.  If it sues to recover the retainage, however, its recovery is subject to the defendant’s counterclaim in recoupment for the actual damages caused by the breach.”).
 
There are many ways to structure a retainage provision.  The percentage of retention – most often 10% – may be reduced or eliminated at some agreed point (say, the 50% completion stage).  It may be reduced at substantial completion to an amount tied to the estimated cost of completing punch list items, to be released upon punch list completion.  Sometimes a portion of it may be held for the duration of warranty obligations.  In New Hampshire, these are all negotiable matters – with one regulatory exception for certain state-funded water pollution control projects.  
 
A performance bond likewise provides protection against the financial impact of a contractor default.  If the performance bond surety cures a default, retainage is no longer needed for that purpose.  But that doesn’t mean the retainage is then turned over to the contractor.  Many performance bonds expressly provide that any retainage must be paid over to the surety as a condition of the surety’s obligations.  Even without this express provision, the surety’s right to retainage is implied by most courts under equitable subrogation principles – which have been recognized by New Hampshire in similar contexts.  Chase v. Ameriquest Mortgage Co., 155 N.H. 19, 27 (2007), is an example (equitable subrogation “applies where one who has discharged the debt of another may, under certain circumstances, succeed to the rights and position of the satisfied creditor.”). 
 
If the owner chooses to apply retainage to cure a contractor’s default instead of resorting to the performance bond, but the retainage ends up being insufficient to fully cure the default, how does this affect the surety’s obligation to finish any remaining scope of work?  In this scenario the owner has impacted the surety’s right to complete the project as it sees fit, and deprived it of money to fund the effort.  This is akin to an owner picking its own completion contractor before giving the surety the opportunity to do so – a circumstance which has been held to absolve the surety of liability under its bond.  Sleeper Village, LLC v. NGM Insurance Co., 2010 WL 3860373 (D.N.H. Oct. 1, 2010).  I expect a similar result would follow the owner’s application of retainage to cure a contractor default.
 
Because invading retainage while a performance bond is still potentially in play is risky business, most owners won’t risk using retainage to complete a project unless the retainage is clearly sufficient to do so – and even then, they are likely to seek the surety’s permission.  The popular AIA-A201 (2017) General Conditions provides for consent of surety to release of retainage to the general contractor at the completion of the project.  It is silent on surety consent to use of retainage to cure a breach, but the implications are the same.
 
There is a wrinkle here.  In New Hampshire, when “a bond refers to and is conditioned on the performance of a specific agreement the latter’s terms become a part of the bond,” Paisner v. Renaud, 102 N.H. 27, 29 (1959). Thus, a usage of retainage expressly allowed in the bonded contract could theoretically moot the need to seek surety consent.  If, say, a bonded general contract expressly permitted the use of retainage to clear subcontractor liens, an owner who uses retainage held back from the general contractor to pay off a subcontractor’s lien has a decent argument against a performance bond surety’s objection.


0 Comments

    Author

    Frank Spinella

    Archives

    January 2026
    December 2025
    November 2025
    October 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly