#31:  Insurance Coverage for the Consequences of Defective Work

7/15/2015

0 Comments

 
Defective construction often has a domino effect, as poor workmanship in one area can damage perfectly good work in others.  A steel beam atop a multi-story steel-framed building, if welded improperly, can fall on and damage properly welded beams below.  The law is clear that a standard commercial general liability policy won’t cover the cost of replacing the poorly-welded beam.  But what about the others?

Consider this scenario:  a contractor builds a home, and months later gets a call from the homeowner complaining of water infiltration where the deck meets the house.  The contractor investigates, and finds out that improper flashing is the culprit and will have to be redone.  The adjacent sills were installed correctly, but they are now damaged and need replacing as well.

On reading his insurance policy, he finds the standard exclusion in section (J)(6) for "[t]hat particular part of real property that must be restored, repaired or replaced because 'your work' was incorrectly performed on it."  He asks his lawyer whether the clause excludes coverage for replacing the sills, pointing out that no defective work was “incorrectly performed on” the sills themselves.  His lawyer checks the latest developments in New Hampshire law, and gives him some good news:  the sills should be covered.  Cogswell Farm Condo. Ass'n v. Tower Group, Inc., 167 N.H. 245, 252 (2015), held that “exclusion J(6) bars coverage for property damage to the defectively constructed portions” but “does not bar coverage for damage to those portions of the units that were not defectively constructed . . . but were damaged as a result of the defective work.”

When the insurance carrier receives the contractor’s claim, however, it is unimpressed by the Cogswell Farm ruling, and denies coverage on the ground that there has been no “occurrence” – defined in the policy as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions“ – to trigger coverage in the first place.  It notes that Cogswell Farm declined to consider whether there had been a triggering “occurrence” because the insurance carriers in that case raised the issue too late.  And it points to the Supreme Court’s admonition in Brown v. Concord Group Ins. Co., 163 N.H. 522, 528 (2012), that “to constitute an ‘occurrence,’ the damage at issue must have been to property other than [the contractor's] work product.”  For this purpose, the carrier maintains, the contractor’s “work product” means all of its work, not just the defective work.

Is the carrier right?  A definitive answer must await a case squarely presenting the issue that Brown did not present: whether damage to elements of the construction that were not defective is considered damage to a different work product for purposes of defining “occurrence.”  But contractors have reason to be optimistic.  A popular treatise on insurance law, quoted in Concord General Mutual Ins. Co. v. Green & Co. Bldg. and Development Corp., 160 N.H. 690, 693 (2010), states that “an occurrence is an accident caused by or resulting from faulty workmanship, including damage to any property other than the work product and damage to the work product other than the defective workmanship."  9A S. Plitt, D. Maldonado & J. Rogers, Couch on Insurance 3d § 129:4, at 129-13 to 129-14 (2005) (my emphasis).

Unless all the subsequent dominoes are insured, CGL policies have diminished value.  As the Alabama Supreme Court recently observed in Owners Insurance Co. v. Jim Carr Homebuilder, LLC, 157 So.3d 148, 155 (2014), “to read into the term ‘occurrence’ the limitations urged by [the carrier] would mean that, in a case like this one, where the insured contractor is engaged in constructing an entirely new building, or in a case where the insured contractor is completely renovating a building, coverage for accidents resulting from some generally harmful condition would be illusory.  There would be no portion of the project that, if damaged as a result of exposure to such a condition arising out of faulty workmanship of the insured, would be covered under the policy.”  The court found coverage for the subsequent dominos.  Perhaps our Supreme Court will do likewise.


0 Comments

#30:  Termination for Cause or Convenience

7/4/2015

0 Comments

 
The concept of termination of a contract for breach (usually referred to as “cause”) is as old as contract law.  If one party materially breaches a contract, the other party is excused from further performance and can end the contract without liability.  “Materiality” is the key here.  “Only a breach that is sufficiently material and important to justify ending the whole transaction is a total breach that discharges the injured party's duties.”  Fitz v. Coutinho, 136 N.H. 721, 725 (1993). 

From the contractor’s perspective, a failure to get paid always feels like a “material” breach.  But that is not necessarily the case.  The Fitz case just mentioned held that “[w]hether a delay in payments is a material breach is a question for the trier of fact to determine from the facts and circumstances of the case,” and affirmed a trial court finding that a failure to make the weekly payments prescribed by the parties’ contract did not qualify as “material.”  Conversely, from the owner’s perspective, a contractor’s poor workmanship feels like a “material” breach.  But that is not necessarily the case either.  McNeal v. Lebel, 157 N.H. 458, 465 (2008) (“so long as any flaws in Lebel's performance did not amount to a material breach . . . the plaintiffs were contractually obligated to allow him to finish the job.”).

Because the materiality of a breach is often debatable, contracting parties may prefer to specify in their written agreement the defaults that will justify termination.  For example, the AIA form A201 (2007) General Conditions of the Contract for Construction allows a contractor to suspend work on 7 days notice if not paid within 7 days after payment falls due (§9.7), and terminate the contract if the work remains suspended for an additional 30 days on account of that nonpayment (§14.1.1).  The Owner may terminate the contract if the contractor fails to supply enough workers or materials, fails to pay subs and suppliers, or repeatedly disregards applicable laws or regulations (§14.2.1).

Invoking specified grounds for termination is not without risk: if a court ultimately finds termination not to have been justified, the party who was wrongfully terminated can sue for breach and recover damages.  This risk is greatest for owners, whose grounds for termination are typically less clear-cut than a contractor’s termination for nonpayment.  Owners can lessen this risk by inserting a clause in their contracts that any purported termination for cause, if ultimately proved to be wrongful, shall automatically be deemed to constitute a termination for convenience.  This is a standard provision in government contracts.  See 48 C.F.R. 52.249-8(g) (“If, after termination, it is determined that the Contractor was not in default, or that the default was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for the convenience of the Government.”)

A termination for convenience clause allows termination of a contract without cause, and specifies the compensation to which the contractor (or subcontractor) will then be entitled.  For example, the AIA form A201 (2007) provides in §14.4.3 that upon termination for the owner’s convenience, “the Contractor shall be entitled to receive payment for Work executed, and costs incurred by reason of such termination, along with reasonable overhead and profit on the Work not executed.”  Some contracts have a less charitable measure of recovery for convenience terminations, limiting the terminated party to payment for work performed and denying any lost profits on work not performed.  In such a case, automatic conversion of a botched termination for cause into a termination for convenience not only insulates the terminating party from breach, but is a real money saver.


When contractors agree with owners (or subcontractors agree with contractors) to such reduced compensation upon termination for convenience, a peculiar and perhaps unintended result is that the owner or contractor can continue to shop the contractor’s or subcontractor’s price throughout the project, and if it finds someone willing to complete the work for less money, it can simply terminate the higher-priced contract and make a change.  Implied obligations of good faith and fair dealing are theoretical restraints against such a practice.  So are transaction costs.  But it can happen.

0 Comments

    Author

    Frank Spinella

    Archives

    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly