#72:  Determining the Amount of a Mechanic's Lien

10/7/2018

0 Comments

 
A contractor is thrown off a job midstream for alleged shoddy work and/or slow performance.  He sues the owner for his unpaid contract balance.  His contract provides for interest and attorneys’ fees if payment is not timely made, so he adds both to his complaint.  The owner then counterclaims for the cost of correcting items of poor workmanship and for the cost of completing the unfinished work (which the owner claims will exceed the unpaid contract balance), and perhaps for delay damages as well.

Suppose the contractor applied for and got a mechanic’s lien attachment on an ex parte basis in the full amount of his claims (unpaid balance, interest and anticipated attorneys’ fees).  If the owner then files an objection to the lien and asks for a hearing, what will be grounds for the judge to reduce or eliminate the lien?

The starting point is the basic mechanic’s lien rule in RSA 447:2 that anyone who furnishes labor or materials to improve another’s property “shall have a lien on any material so furnished and on said structure, and on any right of the owner to the lot of land on which it stands.”  The word “shall” here means what it says.  The lien is a matter of right so long as it is timely and properly perfected.  Timeliness is governed by RSA 447:9, providing that the lien “shall continue for 120 days after the services are performed, or the materials, supplies or other things are furnished.” Perfection is governed by RSA 447:10, providing that a mechanic’s lien is secured “by attachment of the property upon which it exists at any time while the lien continues.”  

Because an attachment is a court order, it is tempting to assume that all of the provisions of New Hampshire’s pre-judgment attachment statute, RSA 511-A, will apply to that effort -- including RSA 511-A:3, which requires “the plaintiff to show that there is a reasonable likelihood that the plaintiff will recover judgment including interest and costs on any amount equal to or greater than the amount of the attachment.”  This statute focuses on the ultimate judgment, where counterclaims will matter; any judgment will necessarily be reduced by a successful counterclaim.  But a number of Superior Court decisions, including Consolidated Elec. Distrib., Inc. v. SES Concord Co., No. 89-C-571/579 (Merrimack County Superior Ct., Nov. 21, 1989), and West Side Dev. Group, LLC v. D’Amour, No. 04-C-018, (Carroll County Superior Ct., March 24, 2004), have held that the provisions of RSA 511-A:3 do not apply to mechanic’s lien attachments, thus relieving the contractor of the burden of proving a reasonable likelihood of getting a judgment at least equal to the lien amount.  Our federal court has followed suit.  H.E. Contracting v. Franklin Pierce College, 360 F.Supp.2d 289 (D.N.H. 2005).

Freed of the burden of showing a likelihood that he will recover a judgment “equal to or greater than than the amount of the attachment,” the contractor will be allowed to lien for the amount of his claim regardless of whether the owner may have a setoff against that amount at trial.  The amount of the lien will be the unpaid contract sum, i.e., the contractually agreed value of the labor and materials furnished.  The owner may be able to argue that defective goods and deficient work must be taken into account in valuing the contractor’s performance, but not all courts will lend an ear to that argument at the attachment hearing, preferring to leave that claim for trial and not gut the lien at the pretrial stage.

Note that the inapplicability of RSA 511-A:3 cuts both ways; a mechanic’s lien attachment will not include “interest and costs” (which for this purpose will include attorneys’ fees).  If those amounts were included in the lien amount ex parte, subtracting them may be the owner’s lone victory at the attachment hearing.

0 Comments

    Author

    Frank Spinella

    Archives

    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly