NH Construction Law
  • Home
  • Blog
  • Links

#108:  Replacement Contractor Issues

12/19/2021

0 Comments

 
When a contractor abandons or is terminated from a construction project before substantial completion, one of the first tasks for the owner/developer (or for the contractor’s performance bond surety if such a bond exists) is to locate and hire a replacement contractor.  If the original contract went south due to defective workmanship issues, the newcomer will be tasked not only with finishing up uncompleted scope, but with correcting existing mistakes.  It is certainly possible, even wise, for the new contractor to disclaim any liability for his predecessor’s work, but at the end of the project teasing apart the respective responsibilities for any issues with the finished product can be challenging.

One of the certainties in life, right up there with death and taxes, is that the price tag for completion will exceed the original contractor’s unpaid contract balance.  Fearful of their own warranty liability, the time-honored approach of completion contractors has been to err on the side of correcting any work that may even marginally impact satisfactory completion of remaining work.  At the bid stage, even with the original plans and specs and any change orders or updated drawings in hand, the completion contractor won’t be able to spot every potential error in the existing work, and so will pad his bid – or insist on a cost-plus arrangement – to protect himself against unseen issues. Cha-ching!

Faced with this, the owner/developer must anticipate that litigation with the original contractor may ensue, and will want to preserve the evidence of how the project was left at the point of abandonment or termination.  Photographing and videotaping the stage of construction before the completion/correction process begins is always smart, but that snapshot-in-time sufferers from the same challenges that the completion contractor faces at bid time; all possible construction defects won’t be observable on Day 1.  It’s a good idea to keep the camera handy to document things when what was once latent becomes patent – and to insist that the completion contractor call out newly observed defects before proceeding with a fix.

If the original subcontractors can be wooed back to the job (or better yet, have already agreed to the assignment of their subcontracts to the owner in the event of the contractor’s termination), there may be a basis for correction of at least their deficient work without additional cost.  This assumes that the completion contractor is required to employ them – a provision that the owner (or performance bond surety) may wish to insist on, but that the completion contractor may resist (why break the huddle with a sub who dropped the ball when the prior QB threw it a pass?).

When the owner sues the original contractor for the difference between the cost of finishing the work and the unpaid contract balance – the usual measure of damages in such cases, see McMullin v. Downing, 135 N.H. 675, 677-78 (1992) – the contractor will of course insist that the completion costs were excessive or unnecessary.  Who has the burden of proof on this issue?  Parem Contracting Corp. v. Welch Construction Co., Inc., 128 N.H. 254, 259 (1986), gives an answer in the analogous context of a terminated subcontractor [Parem] defending a counterclaim by a general contractor [Welch] for costs incurred to complete the sub’s work:

“Welch had the burden in the first instance of proving the extent and amount of its damages. [citation omitted]  It was required to show that the claimed expenditures were incurred solely in completing work that Parem had agreed to perform and obtaining materials that Parem had agreed to supply.  However, once the trial court found that the costs actually were incurred as alleged, it was not permitted to conclude that they ‘could have been avoided’ in the total absence of evidence to that effect.  Parem, not Welch, had the burden of going forward with evidence that all or part of the costs could have been avoided without undue risk or burden” [citations omitted].

This burden-shifting framework should apply equally to owners’ claims against terminated contractors.  Nevertheless, owners would do well to support their costs of completion/correction by documenting deficiencies in workmanship as best they can.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.