NH Construction Law
  • Home
  • Blog
  • Links

#100:  Dealing With Rising Costs

4/29/2021

0 Comments

 
It’s no secret to anyone involved in the construction industry that materials prices have been increasing by leaps and bounds recently.  Steel, copper, PVC, drywall, and particularly lumber prices are dramatically higher compared to a year ago.  And the trend continues to be up.

In the traditional “fixed price” or “lump sum” mode of contracting, a construction project must be delivered by the contractor for the agreed price, subject to whatever contract provisions may justify a price increase – and if increased materials costs are not one of them, the contractor bears all of the risk of those increases.  In the “cost-plus-a-fee” or “time and materials” mode of contracting, materials price increases are generally passed on to the owner – but even here, guaranteed maximum price (GMP) provisions often cap the contractor’s ability to pass on price increases to the owner.

As a hedge against price increases on projects expected to last many months, some contractors buy the bulk of their materials as early in the project as possible, a strategy that works if storage is available at relatively low cost and the purchases are immediately reimbursable (the AIA’s popular A201-2017 General Conditions, for example, allow for payment for materials store off-site “[i]f approved in advance by the Owner”).  Another approach is to negotiate with subcontractors or suppliers to lock in prices for an extended period of time, thereby kicking the price increase risk downstream – but in the present volatile market, subs and suppliers are increasingly reluctant to hold their prices for long, typically not more than 60 or 90 days.  Any delay in the start of construction puts the contractor in a tough position here.

One way to share the risk is through a price escalation clause in the parties’ contract, allowing some or all of a cost increase to be shifted from contractor to owner (or from subcontractor to contractor).  Generally these clauses will have one of two triggers, either a delay or other event beyond the contractor’s control occurring during the project that pushes off the anticipated date of materials purchases, or a stated percentage increase in actual costs compared to some agreed benchmark.  Often the benchmark is indexed costs, for example the producer price index or “PPI” published by the Bureau of Labor Statistics.  Sometimes the benchmark is budgeted costs, i.e., the contractor’s actual buyout costs at bid time (or those of their subs if the subcontract prices are similarly allowed to fluctuate).  That choice is more common in cost-plus contracts as a mechanism to increase the GMP than it is in fixed-price contracts, where the contractor is often reluctant to share its budgeted costs with the owner, thereby revealing its margins.

Owners go along with price escalation clauses for the same reason they go along with differing site conditions clauses; they want to disincentivize contractors from padding their bids to cover themselves for unknown contingencies.  Uncle Sam was among the first to catch on, and for decades has authorized price adjustment clauses for fixed price contracts in the Federal Acquisition Regulations, 48 CFR § 16.203-1, as long as they are “based on increases or decreases in labor or material cost standards or indexes that are specifically identified in the contract.”

Whatever the chosen trigger, price escalation clauses are products of negotiation that can cabin the contractor’s ability to pass on price increases in various ways.  I have seen clauses with floors (e.g., price increases below 5% will be absorbed by the contractor) and/or ceilings (e.g., price increases up to a limit of 15% can be passed on to the owner).  I have seen clauses that adjust the contract price in both directions, affording the owner a price reduction if input costs decrease (probably a waste of ink in the present economic climate).  And almost always the change order process must be invoked, with its timing limitations and waiver possibilities.

While price escalation causes are more common in commercial than in residential construction contracts, the National Association of Home Builders has put out a sample addendum for residential contracts.  Worth a look.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly