#114:  No Damages for Delay -- Maybe, Maybe Not

6/30/2022

0 Comments

 
Delays on construction projects are as common as shells on the shore.  They can arise from contractor fault, owner fault, or events beyond either party’s control – or any combination of these.  Contracting parties contemplate the possibility of delays, and often include contract language to address them – sometimes with clauses precluding a contractor from any monetary compensation for delays, even owner-caused delays.  Such “no-damages-for-delay” clauses can take various forms, but they typically limit a delayed contractor (or subcontractor) to extensions of time for performance in the event of delays beyond the contractor’s control.  While such time extensions may help avoid assessment of liquidated damages, they put no money into the contractor’s pocket for what can often be devastatingly expensive consequences of being on the job longer than anticipated.
 
Because freedom of contract is an overarching principle in the law, courts generally enforce no-damages-for-delay clauses.  Still, contracts excusing a party from liability for the harm he causes have never been favorites of the courts, which have been willing to entertain exceptions to the enforceability of such clauses.  While New Hampshire has yet to tackle this question, most jurisdictions refuse to enforce no-damages-for-delay provisions in certain circumstances, such as “if the delay: (1) was of a kind not contemplated by the parties, (2) amounted to an abandonment of the contract, (3) was caused by bad faith, or (4) was caused by active interference,” Peter Kiewit Sons’ Co. v. Iowa Southern Utilities Co., 355 F. Supp. 376, 397 (S.D. Iowa 1973).  Several states even have statutes disallowing such clauses.  Ohio’s statute, for example, declares that any clause in a construction contract “that waives or precludes liability for delay...when the cause of the delay is a proximate result of the owner’s act or failure to act, or that waives any other remedy...when the cause of the delay is a proximate result of the owner’s act or failure to act, is void and unenforceable as against public policy.”  R.C. 4113.62(C)(1).
 
The “active interference” exception to enforcement of no-damages-for-delay provisions dovetails nicely with New Hampshire's longstanding rule that "
if it can be shown that the performance of the contract was prevented directly or indirectly by the act of the promisee, its non-performance will be excused,” Famous Players Film Co. v. Salomon, 79 N.H. 120, 122 (1918).  No bad faith need be shown.  And the modern trend elsewhere is that “a plaintiff contractor or subcontractor claiming active interference on the part of the defendant owner or contractee need only to show that the defendant committed an affirmative, willful act that unreasonably interfered with the plaintiff’s performance of the contract, regardless of whether that act was undertaken in bad faith.”  Tricon Kent Co. v. Lafarge North America, Inc., 186 P. 3d 155, 161 (Colo. App 2008).
 
One example of active interference is issuance of a notice to proceed before the jobsite is ready for the contractor’s work.  U.S. Steel Corp. v. Missouri Pacific Railroad, 668 F.2d 435, 439 (8th Cir. 1982).  After commencement, suspension of work by the owner beyond the time reasonably justifiable can likewise overcome a no-damages-for-delay clause – regardless of other contract language affording the owner a right to suspend.  Sarasota County v. Southern Underground Industries, Inc., 333 So.3d 285, 288 (Fla. App. 2022).  Indeed, schedule and sequencing changes have been found to justify an award of delay damages even in the face of other contract provisions giving one party the right to dictate progress and sequence of the other party’s work.  J.J. Brown Company, Inc. v. J.L. Simmons Co., Inc., 2 Ill. App.2d 132, 140, 118 N.E.2d 781 (1954) (“The provision of the subcontract giving defendant the right to direct the sequence or general progress of work does not release it from liability for delay.  It implies an obligation on the part of the general contractor to keep the work in such a state of forwardness as to enable the subcontractor to perform within a limited time.”).
 
The common thread here is that owners must give their contractors (and contractors must give their subcontractors) a fighting chance at timely performance – and if they interfere with that chance, a no-damage-for-delay provision likely won’t save the day.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.