#48:  The Use and Abuse of Liquidated Damages

9/29/2016

0 Comments

 
Getting a project completed on time is often crucial to a commercial owner, who must forego the efficiencies or even the business opportunities which motivated him to build the longer the project is incomplete. Making delayed completion a breach of contract is all well and good, but proving the damages that will flow from such a breach can be difficult; the legal standard for recovery of damages requires proof by a preponderance of the evidence that profits would have been realized or increased but for the delay, as well as reasonable certainty as to their probable amount.

It is precisely for such situations that liquidated damages clauses are used in many construction contracts. Damages are agreed to, or “liquidated,” in advance, usually in a particular amount per day of delay, thereby relieving the owner of the burden of proving actual damages. But because the law aims to make the non-breaching party whole and not give him a windfall, courts impose restrictions on the ability to recover liquidated damages – as a check against the possibility that the amount fixed by agreement may be wildly divergent from actual damages, thereby constituting a penalty. A liquidated damages clause will be enforceable if “(1) the damages anticipated as a result of the breach are uncertain in amount or difficult to prove; (2) the parties intended to liquidate damages in advance; and (3) the amount agreed upon is reasonable and not greatly disproportionate to the presumable loss or injury.” Holloway Automotive Group v. Lucic, 163 N.H. 6, 9-10 (2011).

The first two of these elements are rarely problematic in a construction contract. Almost always, the fight will be over the third element: was the liquidated amount reasonable? Our courts “employ a two-part test to determine whether a liquidated sum is reasonable. First, we assess whether the amount 'was a reasonable estimate of difficult-to-ascertain damages at the time the parties agreed to it.' Next, we ask whether actual damages are 'easily ascertainable' after a breach. '[I]f the actual damages turn out to be easily ascertainable, we must then consider whether the stipulated sum is unreasonable and grossly disproportionate to the actual damages from a breach.' If the stipulated sum is grossly disproportionate to easily ascertainable, actual damages, the provision is an unenforceable penalty, and the aggrieved party will be awarded no more than the actual damages.” Holloway, 163 N.H. at 10.

Let's break this down. The first inquiry is prospective as judged at the time of contracting: was the amount chosen a reasonable estimate of what appeared at the time to be hard to prove with precision? The second inquiry is retrospective: have subsequent events shown that actual damages are easy to prove – and if so, was the original estimate in the ballpark? Thus, the reasonableness of the estimate is judged both prospectively and retrospectively.

Most liquidated damages clauses are premised on delays in substantial completion rather than final completion. The reason is not hard to see: substantial completion is the stage of progress at which the project can be used by the owner for its intended purposes, and once the owner can use it, damages for delay no longer accrue. Nevertheless, I have seen contracts purporting to impose liquidated damages for late final completion, and even for late completion of interim milestones. Whether such provisions are enforceable in court is another matter. My guess is that these are likely to be deemed unenforceable penalties.

If a liquidated damages clause is unenforceable, the non-breaching party can still recover any proveable actual damages. General Linen Services, Inc. v. Franconia Investment Associates, L.P., 150 N.H. 595, 600 (2004). The more interesting question is whether a nonbreaching party can choose to sue for actual damages in the face of a valid liquidated damages clause. As long as the contract expressly gives an option to pursue either, the answer appears to be Yes – although “where an election is permitted, the election of one remedy bars pursuit of the other,” because “the right to recover liquidated damages and the right to recover actual damages are mutually exclusive remedies,” Orr v. Goodwin, 157 N.H. 511, 517 (2008). 
0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    August 2026
    July 2026
    June 2026
    May 2026
    April 2026
    March 2026
    February 2026
    January 2026
    December 2025
    November 2025
    October 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly