#50:  Change Order Disputes

11/25/2016

0 Comments

 
Owner and contractor sign a contract for performance of a defined scope of work. The owner changes the scope in a way that will increase the contractor's costs. The contractor pulls out the contract, looks at the “change order” clause, and follows the stated procedures for getting extra compensation. Sounds simple, doesn't it?

In practice, it rarely is that simple. There can be disputes over whether the initial scope of work has really changed. There can be disputes over who is responsible when the contractor is obliged to alter his planned means and methods of construction in order to accommodate unanticipated circumstances. There can be disputes over pricing.

To speak of a change “order” smacks of owner discretion and control, but from a legal perspective the focus is usually on the contractor's rights. “A change order is a charge for work not included in a contract's scope of work.” H.E. Contracting v. Franklin Pierce College, 360 F.Supp.2d 289, 292 n.3 (D.N.H. 2005). The “change” part arises from an alteration of either the work initially designated or the means of performing it. The “order” part arises from an actual or implied directive to perform the altered task, but in the latter case “order” is a bit of a misnomer – the common terminology of change orders being “issued” by an owner or architect doesn't quite fit. An owner or architect will not issue a change “order” he doesn't agree with, yet the courts often indulge in the fiction that he has done exactly that.

Many owners attempt to protect themselves from this result with contract language specifying that no change orders are allowable unless agreed on by the owner in writing. In the H.E. Contracting case, the contract stated “No claim for extra work or cost shall be allowed unless the same was done in pursuance of the written order of the Engineer, approved by the owner.” The Court ruled that such provisions are enforceable “unless the owner has actual knowledge of the additional work and is not prejudiced by the contractor's failure to comply with the writing requirement.” Id. at 294. This suggests that if the work truly is “additional,” and the owner is paying reasonable attention to what is happening on site and does not step in to stop it, the additional work will generally be compensable even if the owner never picks up a pen. The legal principle here is familiar. Like all contract modifications, change orders must be agreed to either expressly (typically demonstrated by signing a piece of paper) or impliedly (typically shown by a direction to the contractor to perform the change under circumstances that yield a reasonable expectation of extra compensation). Resolution of change order disputes almost always boils down to a search for those circumstances, and hence for that implied consent.

This does not mean that owners are at contractors' mercy whenever there are scope changes. From the owner's perspective, if a change is to have a price tag associated with it, the owner wants to know what that price will be before blessing the change. It is common to find contract provisions for submission of a claim before the additional work is started, with an itemized breakdown of additional costs. Such provisions are enforceable. So are provisions for how change orders will be priced in the event of disagreement on the amount (e.g., unit prices stipulated in advance, or documented time and materials charges with a markup stipulated in advance). Owners are not expected to issue blank checks for extra work.

Conversely, change orders can embrace more than the raw cost of constructing the new or altered work. Suppose that an owner's indecision or change of mind causes delays to the job, leaving the contractor with extended general conditions and additional time on the job for which he seeks compensation through the change order process. More often than not, the courts will award compensation for these as well, unless specific contractual language excludes them.

The common thread here is that contractual provisions matter – but so does fairness to both sides.
0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    August 2026
    July 2026
    June 2026
    May 2026
    April 2026
    March 2026
    February 2026
    January 2026
    December 2025
    November 2025
    October 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly