NH Construction Law
  • Home
  • Blog
  • Links

#61:  Excusing Delays in Completion

10/30/2017

0 Comments

 
Under the rule that parties to a contract have a duty not to hinder or delay each other’s performance, an owner cannot recover damages for a delay in completion of the contractor’s work if the owner or his agents slowed down the contractor’s performance.  But sometimes a third party, or the government, or a casualty or other circumstances will delay final completion of the project of which the contractor’s work is only a part, without hindering the contractor’s own work.  In such a case, is the contractor excused from meeting his contractual deadline on the theory that the need for strict compliance with his deadline has become moot?
 
An example will illustrate the issue.  Suppose an owner contracts separately with two prime contractors -- let’s call them “Eastbound” and “Westbound” -- each of whom is to build 500 feet of a one-thousand foot tunnel, each at the same unit price per foot, each in 100 days starting on the same day and ending at the same designated point smack in the middle of the mountain.  If the tunnel is not completed on time and no extensions have been granted, consider how damages (whether actual or liquidated) should be assessed if:

A. 
Eastbound reaches the midpoint 10 days late, and Westbound reaches the midpoint 50 days late; or
 
B.  With Westbound well behind schedule, Eastbound -- who is tunneling at the rate of five feet per day and is thus on pace to complete on time -- takes seven weeks off to do a different job and reaches the midpoint 49 days late, while Westbound reaches the midpoint 50 days late.
 
Under both scenarios Eastbound will argue that it is off the hook because its failure to meet its target completion date did not delay opening the tunnel given Westbound’s greater delay.  The only difference is that under scenario B, Eastbound could have finished on time but chose instead to take advantage of an opportunity to moonlight when some unanticipated “float” fell into its lap.
 
Contract law recognizes the doctrine of “frustration of purpose,” which “assumes the possibility of literal performance but excuses performance because supervening events have essentially destroyed the purpose for which the contract was made.”  Perry v. Champlain Oil Company, 101 N.H. 97, 98 (1957).  Normally the doctrine excuses a party’s performance when the value of the contract to the party seeking to be excused has been destroyed by an unanticipated and fortuitous event.  But here, timely performance has turned out to be of no value to the owner, who is not the one seeking to be excused from the contractual deadline.  Moreover, performance of the entire contract has not lost its value to the owner; only the completion deadline has lost its value, and only for a relatively short time.  The commercial frustration defense is a poor fit.
 
“No harm,” then, does not necessarily mean “no foul.”  But it may mean “no remedy.”  An owner who must prove actual damages (because there is no enforceable liquidated damages clause), but cannot pin loss of use of the project as a whole on Eastbound, is unlikely to be awarded any damages for the breach.  If, however, liquidated damages are sought, the result could be different, since proof of actual damages is not necessary for enforcement of a liquidated damages provision.
 
Scenario B presents an additional issue.  If Eastbound was on pace to finish on time and Westbound was lagging, the owner could have issued change orders adding 100 feet to Eastbound’s scope and deducting 100 feet from Westbound’s scope, resulting in faster completion of the tunnel (120 days rather than 150) at no additional cost.   By not
keeping Eastbound on site, the owner signaled that prompt completion was not important to the purpose of the contract, and may have waived his right to complain about late completion.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly