#65:  Unjust Enrichment Recovery for Verbal Change Orders

3/24/2018

0 Comments

 
Given the importance of nailing down any changes to an original scope of work along with their price and schedule effects, many construction contracts require change orders to be in writing, and even define change orders as written instruments.  Section 7.2.1 of the A201 (2017) is typical: “A Change Order is a written instrument prepared by the Architect and signed by the Owner, Contractor and Architect.”  Some contracts are even more limiting, expressly stating that if extra work is done without a signed change order, no additional compensation can be claimed.
 
What if an owner orders a change but never prepares the written change order?  What if the contractor prepares a change order himself but the owner ignores it?  Should he suspend work, and risk being in breach? There may be another option.  If he proceeds with the work on the reasonable expectation of getting a change order signed later and doesn’t get it, he still has a shot at “unjust enrichment” recovery -- a remedy allowed by courts when an individual receives “a benefit which would be unconscionable for him to retain,” Clapp v. Goffstown Sch. Dist., 159 N.H. 206, 210 (2009).  
 
Unjust enrichment recovery “may be available to contracting parties if the benefit received is outside the scope of the contract,” Axenics, Inc. v. Turner Construction Co., 164 N.H. 659, 670 (2013), but not if the parties’ contract addresses the subject matter of the claim.  In Axenics a subcontractor’s claim against a general contractor for “failure to properly coordinate construction” was rejected because the GC’s coordination responsibility and the sub’s entitlement to payment for any resulting extra work or extra costs “was addressed in the subcontract itself.”  The Court explained that “the terms of the subcontract expressly addressed the possibility of delays and hindrances as well as the process by which Axenics would receive payment for any extra work that it performed because of change orders.  The subcontract also established a mechanism for proceeding when Axenics believed the ‘work to be beyond the scope of’ the subcontract, and delineated Turner’s responsibilities for coordinating changes to the work.  Since the subcontract governed the subject of Axenics’ unjust enrichment claim, and the subcontract was not abandoned by the parties, the trial court erred in allowing Axenics to recover against Turner under a theory of unjust enrichment.”
 
Notice that Axenics did not seek compensation for an added scope of work, but for making an existing scope more expensive to perform.  Added scope sounds like a candidate for unjust enrichment on grounds that “the benefit received was outside the scope of the contract,” id.  But I hesitate to equate a contractual scope of work with “scope of the contract.”  Contractors speak that way.  Judges don’t.  For them, “scope of the contract” is broader, encompassing not only the work to be done but all of the terms and conditions impacting the performance of that work.  
 
Still, any contractual provision can be modified by the parties -- including a provision requiring that change orders be in writing.  “Parties to a contract can not, even by an express provision in that contract, deprive themselves of the power to alter or vary or discharge it by subsequent agreement.  An express provision in a written contract that no rescission or variation shall be valid unless it too is in writing is ineffective to invalidate a subsequent oral agreement to the contrary.”  Prime Financial Group, Inc. v. Masters, 141 N.H. 33, 37 (1996). Ordering extra work that both parties should reasonably anticipate will entail extra costs, particularly when accompanied by insistence that it be done promptly before a change order is prepared and signed, is evidence from which a court might infer an agreement to modify the requirement that change orders must be signed before extras can get paid.

0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    July 2026
    June 2026
    May 2026
    April 2026
    March 2026
    February 2026
    January 2026
    December 2025
    November 2025
    October 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly