NH Construction Law
  • Home
  • Blog
  • Links

#28:  Excusing the Failure to Meet a Performance Spec

4/26/2015

0 Comments

 
A few months back I blogged about design and performance specs, and noted that difficulties in meeting a performance spec can be excused when implementing it is impossible or commercially impracticable (i.e., impossible to achieve or achievable only at excessive cost).  In such a case, the contract documents call for a result that cannot reasonably be expected of the contractor under the parameters given.

The problem can arise whenever the designing engineer fails to appreciate how his specs are interrelated, and calls for two things that are in tension with each other.  To take a simple example, if a given design for a turf field requires permeability of X inches per hour (a performance spec) but also requires the underlying base stone to contain a high minimum percentage of small particles (a design spec), the net result will be that the air voids needed for good drainage will be filled with too many fines to achieve the required permeability.

Many contracts require the contractor to call to the architect’s or engineer’s attention any inconsistencies of this sort that the contractor happens to notice.  Unless the tension is glaring, however, a contractor will typically not spot the problem at bid time.  Even if subcontractor bids have been solicited for portions of the overall specs in advance of the contractor’s own bid, chances are they will not have been solicited very far in advance, and the most experienced specialty subcontractor could fail to notice a latent problem―particularly where other specs imposing some physical constraints on the options available to implement a given performance requirement happen to be buried in another spec section.

Some courts hold that the constraints imposed by those other specs can excuse a performance spec simply by unduly restraining the contractor’s choice of means and methods to achieve it.  That was the case, for instance, in Niagara County v. R & D Engineering, P.C., 298 A.D.2d 971, 973 (2002), a suit by a Water District against Goulds Pumps for furnishing pumps with “excessive vibration” beyond the maximum levels required in the specs.  Because the contract documents included “at least seven pages of the ‘details of construction’ for the pumps and their motors,” the Court found that “the vibration specification was not a performance specification, inasmuch as it cannot be said that Goulds was ‘free to choose the materials, methods and design necessary to meet the objective or standard of performance.’"

Other courts hold that “when a contract contains a mix of both design and performance specifications, the contractor may defend on an implied warranty theory if the design specifications are defective to the degree that adherence to them results in an article that fails to satisfy a stated performance specification."  R.J. Crowley, Inc. v. U.S., 1990 U.S. App. LEXIS. 21618 (Fed. Cir. 1990).

Still other courts hold that meeting a performance spec is excused if meeting related design specs renders the performance spec commercially impracticable.   An example is Waldinger Corp. v. CRS Group Engineers, Inc. Clark Dietz Div., 775 F.2d 781, 789 (7th Cir. 1985) (“We conclude that Ashbrook's inability to supply a filter press that would both satisfy Dietz's mechanical specifications and perform as required is sufficient to establish that performance of its contract with Waldinger was commercially impracticable.”).

Whichever of these approaches is taken, the basic concept is the same.  If design specs foreclose a contractor’s options to the point that meeting a performance spec becomes impossible or impracticable, failure to meet the performance spec will be excused. 

The risk to the contractor is that commercial impracticability, like beauty, is in the eye if the beholder.  A contract is commercially impracticable when performance would cause "extreme and unreasonable difficulty, expense, injury, or loss to one of the parties." Restatement (Second) of Contracts § 261 cmt. d (1981).  One judge or jury may have a different view than another of what is “extreme and unreasonable.”


0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly