NH Construction Law
  • Home
  • Blog
  • Links

#7:  Statutes of Limitation, the Discovery Rule, and Statutes of Repose

6/4/2014

0 Comments

 
Statutes of limitations – deadlines for bringing a lawsuit – are premised on the notion that the passage of time naturally tends to result in lost evidence, disappearing witnesses and faded memories, eventually reaching the stage where justice cannot confidently be dispensed by the courts and forcing a defendant to defend becomes unfair.  In New Hampshire this length of time is generally three years from the time of the breach of duty – and in the construction setting, this will typically be a breach of a contractual duty.

If forcing a defendant to defend a stale claim is unfair, so is shutting out a plaintiff who couldn’t sue within three years of the breach because he or she didn’t have a fair opportunity to discover it―for example, when a latent construction defect first surfaces after three years. In that case the three-year clock will start ticking only when the breach is or reasonably should have been discovered.  Naturally enough, lawyers call this the “discovery rule.”

You can see the tension between these twin fairness concerns.  Theoretically, the discovery rule could allow a lawsuit to be brought decades after a breach, making defense an iffy proposition.  But in the construction setting, the Legislature has restruck the balance by enacting an eight year statute of “repose” – a deadline after which breaching parties can rest easy even if their breach has not yet been discovered.  RSA 508:4-b states:

“Except as otherwise provided in this section, all actions to recover damages for injury to property, injury to the person, wrongful death or economic loss arising out of any deficiency in the creation of an improvement to real property, including without limitation the design, labor, materials, engineering, planning, surveying, construction, observation, supervision or inspection of that improvement, shall be brought within 8 years from the date of substantial completion of the improvement, and not thereafter.”


There are some exceptions in the statute, but in general a claim is extinguished eight years after substantial completion regardless of whether the breach has yet been discovered.  In practical effect, the statute of repose is simply a cap on a plaintiff’s invocation of the discovery rule.  If the plaintiff knew or should have known of the breach within five years of substantial completion, the statute of repose isn’t really needed, because the statute of limitations will shut the plaintiff out anyway after eight years.  But if the breach is first discovered (or reasonably should have been discovered) more than five years after substantial completion, the repose clock will run out before the limitations clock does.  The plaintiff’s usual three-year post-discovery deadline is shortened by one day for each day beyond five years from the date of substantial completion that discovery occurred.

Note that neither the discovery rule nor the three year period applies to contracts for the sale of goods.  Unless the seller has warranted future performance of the goods for some longer period of time, the limitations period is four years from the date of sale, even if a problem with the goods is not discovered or reasonably discoverable until after those four years have expired.  (This can sometimes put a contractor in a pinch.  If you inadvertently build a building with defective goods, and the defect is first discovered by the owner more than four years after you bought those goods, the discovery rule may allow the owner to sue you, but you will have no recourse against the supplier!)

Whatever the statutory deadlines are, contracting parties are free to alter them by agreement, both as to length and as to triggering event – and many of them do.  The popular AIA form contract A201-2007, for example, overrides the discovery rule: “As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion.”  It is obviously smart to check your contract language at the first sign of trouble.  If you don’t, you may discover that SOL stands for something other than “statute of limitations!”


0 Comments



Leave a Reply.

    Author

    Frank Spinella

    Archives

    May 2025
    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly