NH Construction Law
  • Home
  • Blog
  • Links

#23:  The Consequences of Shop Drawing Review and Approval

12/19/2014

3 Comments

 
There is more than one way to build a project to the plans and specs that Architects and Engineers provide.  The “means and methods” for doing so are typically up to the contractor.  But sometimes those means and methods are subject to advance scrutiny by the design professional, through the “shop drawing” submittal process.

As the popular AIA A201 General Conditions of the Contract for Construction (2007) explains in Section 3.12.4, shop drawings “demonstrate the way by which the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals.”  Section 3.12.5 requires the contractor to review shop drawings “for compliance with the Contract Documents, and approve and submit to the Architect Shop Drawings, Product Data, Samples and similar submittals required by the Contract Documents.”  By the act of submitting them, the contractor warrants that he has “(1) reviewed and approved the shop drawings; (2) determined and verified materials, field measurements and field construction criteria related thereto, or will do so; and (3) checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents.”  Section 3.12.6.

At that point, the Architect’s own review kicks in―but it is more limited.  Section 4.2.7 says that a design professional’s review of shop drawings is "only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents."   The phrase “design concept” is undefined, and vague enough to preclude the argument that an Architect’s shop drawing approval incorporates the drawing into the Contract Documents. 

The Catch 22 for the contractor is that he has no choice but to implement approved shop drawings, yet he is on the hook if they don’t conform to the Contract Documents.  Section 3.12.8 says that “The Work shall be in accordance with approved submittals except that the Contractor shall not be relieved of responsibility for deviations from requirements of the Contract Documents by the Architect’s approval of Shop Drawings.”  Since the contractor must implement that approved drawing, in practical effect it is indistinguishable from any other plan or spec in the Contract Documents that the Contractor must implement―except that the contractor “owns” it; the Architect does not.  The drawing effectively becomes part of the design, but the only part of the design that a contractor implements at his own risk.

How great is the risk that an approved shop drawing will come back to haunt the contractor despite Architect approval?  This is where human nature kicks in.  Because the Architect who approves a shop drawing is normally the same person signing off on compliance with the Contract Documents for purposes of payment and substantial completion, any “deviations from the requirements of the Contract Documents” arising from that shop drawing are unlikely to be called out.  Subjecting the contractor to liability for repair and replacement of the “approved” item could subject the Architect to a bit of embarrassment as well.  But even if the Architect certifies compliance with the Contract Documents, that won’t relieve the contractor of liability under his warranty.   Section 9.10.4 makes sure of that (“The making of final payment shall constitute a waiver of Claims by the Owner except those arising from . . . failure of the Work to comply with the requirements of the Contract Documents . . .”).

If Architect approval doesn’t get the contractor off the hook to the owner, does it put the Architect on that hook with him?  That depends.  An Architect who didn’t catch or correct an error in a shop drawing and approved it could well be liable to the owner if his contract doesn’t absolve him in advance.  The AIA B101 Standard Form of Agreement Between Owner and Contractor (2007) attempts to do exactly that, parroting the A201 in providing that review is “only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents” (Section 3.6.4.2).  Once again, “design concept” is undefined.

No surprises here, when you remember what AIA stands for.


3 Comments
AOS
12/31/2020 09:13:15 pm

Thank you so much for your clear explanation of the consequences and liabilities that may fall upon an Architect & Contractor after a Shop Drawing is approved. I have encountered a Practice Exam question on who (Contractor or Architect) is liable if a shop drawing gets approved, when the shop drawing deviated from the contract documents in some way.

This is something that's very tricky to understand in the contract alone, but your explanation helped me so much. Thank you again.

Reply
WILLIAM B MEDELLIN link
7/6/2022 01:10:17 pm

In a situation where the Contractor installs a system without submittal and approval of shop drawings, is the Architect liable if he approves payment for such installation?
Thank you for your assistance
William

Reply
Whitney Hale
7/25/2022 05:52:00 pm

Architect's do not 'approve' shop drawing submittals. They review only.

Reply



Leave a Reply.

    Author

    Frank Spinella

    Archives

    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.