NH Construction Law
  • Home
  • Blog
  • Links

#132:  Written Change Order Requirements

12/30/2023

1 Comment

 
Many construction contracts and subcontracts, both residential and commercial, provide that any addition or deletion from the scope of work described in the contract must be documented by a written change order.   The purpose of these written change order requirements is obvious: to avoid disputes down the road over the existence of, extent of, or price and time effects of changes to the work.
 
In the press to get a project completed, contractors and their customers sometimes ignore such contract language, agreeing on a change but failing to get a written change order signed.  Does that failure doom additional compensation (or credit) for an agreed upon change to the work?
 
A few years back I blogged (#65) on the difficulty of unjust enrichment recovery for verbal change orders in the face of contractual requirements for written change orders.  But there are other approaches that can save the day.
 
The most common scenario for getting around a contract provision for written change orders arises from an implied waiver of the requirement.  An example is D.M. Holden, Inc. v. Contractor’s Crane Service, Inc., 121 N.H. 831, 835 (1981), which affirmed an award of damages for extra work despite a contract provisions that “no payment for ‘extras’ would be made unless the work was approved in advance and in writing,” finding that the provision had been disregarded by the parties and impliedly waived.  Where I see this most often is in time crunch settings, with the need for quick action forgiving a lapse in the paperwork.  See Worcester Air Conditioning Co., Inc. v. Commercial Union Ins. Co., 439 N.E.2d 845, 848 (Mass.App. 1982) (“The judge’s finding that it was the practice of the subcontractor and plaintiff to proceed without a written change order where something had to be done quickly justifies the conclusion that they impliedly waived the requirement of a written change order.”).
 
When a contractor’s or subcontractor’s extra work is specifically approved by the owner or contractor, courts tend to allow recovery despite written change order requirements.   Ekco Enterprises, Inc. v. Remi Fortin Construction, Inc., 118 N.H. 37, 41 (1978), is an example: “Although the contract did specify that extra work was to be requested and agreed to in writing, the master correctly ruled that this requirement did not bar recovery for extras, improvements and substitutions made with Ekco’s full knowledge and approval.”
 
The issue of waiver arises only when a party is suing under the contract.  But there are other theories of recovery that can be resorted to, such as quantum meruit.  (See Blog #119)  R. J. Berke & Co., Inc. v. J. P. Griffin, Inc., 116 N.H. 760, 765 (1976), is apt here: “Whatever its merits, the issue of waiver is irrelevant insofar as Berke’s recovery is not on the contract but in quantum meruit.  In the absence of some explicit understanding between the parties that quantum meruit for extras would be barred . . . they were properly included in the calculation of the gross benefit conferred.”
 
As these cases make clear, written change order requirements in construction contracts will not always bar recovery in the absence of the writing.  1 Philip L. Bruner and Patrick J. O’Connor, Jr., Bruner and O’Connor on Construction Law § 4:39 (2010) notes: “The principle of strict enforcement of ‘written order’ requirements is now a pale shadow of its former existence. Since the mid-20th century, the judiciary has recognized the fundamental distinction between authorized changes and written changes, and between the authorization itself and evidence of authorization, and generally has enforced authorized orders in whatever form given.”
 
That being said, the original purpose behind written change orders still holds.  Proving a waiver of the requirement, proving the express direction to perform concededly extra work, and proving a basis for quantum meruit recovery are far more difficult tasks than simply pointing to a signature on a written change order.  If your contract requires such a writing, it is foolish to ignore it and take the risk of being able to prove a basis for forgiving the lapse.

1 Comment
Frechette Chimney Sweeping link
1/8/2025 01:41:48 am

Thank you for sharing such a detailed analysis on the importance of written change orders in construction contracts. The discussion on the waiver of written change order requirements, particularly in time-sensitive situations, is particularly insightful.

At Frechette Chimney Sweeping, based in Portland, ME, we also understand the critical importance of clear, documented agreements, especially when it comes to services like chimney sweeping. Similar to construction contracts, we ensure that all work related to chimney inspections, sweeping, and repairs is properly outlined, often with a written agreement or estimate for our clients’ peace of mind. This helps to avoid any misunderstandings regarding scope and cost, while ensuring that we can quickly and efficiently address any changes that arise during the service.

Whether it's handling chimney maintenance or navigating a change order in construction, clear communication and documentation are key to maintaining successful outcomes. We’re committed to providing top-notch chimney services in Portland, ME, and beyond, while ensuring transparency and professionalism in all of our engagements.

Reply



Leave a Reply.

    Author

    Frank Spinella

    Archives

    April 2025
    March 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    April 2024
    March 2024
    February 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014

    Categories

    All

    RSS Feed

Proudly powered by Weebly